(Day 1): Work finally started on 27/09/2012 - what a relief! We had lots of rocks - some as big as Mazda 2. Removal of rocks was included in the price and so we were not worried.
The soil was hard when dry but very sticky when wet. Preparation for concrete slab.
Lots of huge rocks. Better to include price for removal of rocks in the contract to avoid surprises.
Pipes for rain water, sewege and drains being laid underneath the soil. The first drain here colored in pink is actually not installed at the right spot which we discovered much much late due to which our drain pipe is now on the side of the piller instead of being at the back. Bad job by Metricon.