Wednesday, 5 June 2013

(250 days): 26 days left to the end of the building contract. The contracted period to handover of the house is 276 days which finishes in end June 2013. M is going at a pace of an snail - taking three weeks to finish one item. From our last site inspection, the site supervisor said 3-4 weeks. Well that 4 weeks is finishing this Friday the 7th June, 2013 but still no where near to the handover. I am fed up with M. Last week I just said to the construction manager that you do not need to fix anything I will do it, just handover the house. But that too they can not do due to building code I think.

Few building faults our independent inspector picked up:-

1. Defective Flashing at the front of the portico: Water fall back towards the wall. Flasing is dinted and damaged and has excessive silicon.
2. Exposed yellow gas pipe from the wall.
3. Water pipe lying above the ground and not under.
5. Rusted rear door garage hinges and missing screws.
6. All door hinges pins sticking out.
7. Door handles smeared with paintings.
8. Excess door margins of the cupboard greater than 5 mm.
9. Defective paintings as marked.

These are over and above the six defects we identified. We are glad that we did use independent surveyor to check our house. Worth doing it.

Thats all I have to say .... Should I be happy with Metricon's services???? Leave it upon you.